British Policy
Trident Replacement:
Assessing UK Security Needs and Nuclear Policy
Back to the Main British Policy page
The Future of the Strategic Nuclear Deterrent: the Strategic Context,
Defence Committee Inquiries
Annex C
Investment at the Atomic Weapons Establishment
Background
1. In the early 1950s, the main research and development
activity in support of the UK's atomic weapons programme were transferred
from Fort Halstead near Sevenoaks to a former air base near the village
of Aldermaston in Berkshire. Since then, all the UK's atomic and nuclear
weapons have been designed and manufactured by the Atomic Weapons Establishment
(AWE, formerly Atomic Weapons Research Establishment) on this site and
a neighbouring facility near Burghfield.
2. In 1993, AWE moved from its position as a Government establishment
to one which was still Government-owned but operated by a private contractor.
Nuclear licensing was introduced in 1997: site licenses and discharge
authorities for Aldermaston and Burghfield were granted by the Nuclear
Installations Inspectorate and the Environment Agency. This brought the
AWE sites under the same regulatory controls as the civil nuclear industry.
On 1 April 2000 - co-incidentally, fifty years to the day after its foundation
- and following a competition, the Ministry of Defence placed a contract
with a new company, AWE Management Limited (a consortium comprising Lockheed
Martin, Serco and BNFL) to manage and operate the two sites at Aldermaston
and Burghfield. The contract was initially awarded for an initial period
of 10 years with an option to extend to 25 years with access to private
finance. This option was taken up in 2003.
Capability at the Atomic Weapons Establishment
3. A major feature of this new contract was for the replacement
of many of the major science, manufacturing and assembly facilities on
the two sites. This was driven by three factors. First, over 80% of the
infrastructure at Aldermaston and Burghfield pre-dates 1960 and was becoming
increasingly difficult and expensive to sustain. Second, the introduction
of a moratorium on nuclear weapons testing required the introduction of
significant new methods to underwrite the safety and reliability of the
UK's nuclear weapons stockpile. This is all the more important as the
UK is the only recognised Nuclear Weapon State whose nuclear deterrent
is wholly dependent on a single warhead design. As has been reported in
detail elsewhere[
1], the UK has introduced a major
science-based programme to ensure we can retain the current very high levels
of confidence in the safety and performance of the stockpile. This approach
requires investment in a range of new facilities, such as super-computers,
high energy lasers and hydrodynamics facilities. The nuclear regulatory
regime also rightly imposes stringent safety requirements on the establishment
itself, which are increasingly challenging to meet without additional investment
in facilities built to modern safety standards.
4. When AWE ML's initial contract was awarded, it was recognised
that a detailed appraisal would be required of the condition of the infrastructure
and skills base within the establishment to ascertain whether this was
sufficient to deliver the requirement set out in the 1998 Strategic Defence
Review, specifically:
"For as long as Britain has nuclear forces, we will ensure that
we have a robust capability at the Atomic Weapons Establishment to underwrite
the safety and reliability of our nuclear warheads, without recourse to
nuclear testing. There are no current plans for any replacement for Trident,
and no decision on any possible successor system would be needed for several
years. But we have concluded that it would be premature to abandon a minimum
capability to design and produce a successor to Trident should this prove
necessary."[
2]
5. This appraisal has now been completed and the Written
Ministerial Statement made by the Secretary of State for Defence on 19
July 2005 marked the end of the process to agree contract amendments with
AWE ML to deliver the new programme.
The Future Programme at the Atomic Weapons Establishment
6. Under the revised contract the Ministry of Defence intends
investing on average an additional sum of some £350M per annum at
AWE over each of the next three years. The objective of this investment
will be to sustain the core capabilities required to meet the MOD's requirements.
The programme falls into three broad categories: upgrading of a range
of research facilities to underpin the science programme that enables
AWE to underwrite the safety and performance of the warhead; the refurbishment
of some of the key infrastructure on the sites; and investment in sustaining
core skills within the Establishment.
Science Facilities
7. The programme at AWE is focussed on providing assurance
of the safety and effectiveness of the UK's stockpile of operational warheads
for use on the Trident D5 missile. To provide assurance of warhead safety
and reliability without undertaking full-scale testing, scientists must
be able to demonstrate their understanding of the physical and chemical
processes that occur within the warhead. In addition, age-related changes
must be investigated and the implications understood. Computer simulations
are used to predict the effect of future changes and warheads are routinely
withdrawn from the operational stockpile for forensic examination, which
further improves the accuracy of these simulations. The specific capabilities
required to undertake this assurance work fall into three main areas -
high performance computer simulation, hydrodynamics and high energy density
physics. Experiments and models are used to test theoretical understanding
of the scientific principles and processes involved. This warhead assurance
work represents the core activity presently undertaken at AWE.
8. Particular projects to be taken forward include concept
and design studies for the replacement of major facilities for hydrodynamics
experiments; and the development of a new high energy laser facility (Project
Orion).
Manufacturing, Assembly and Disassembly Facilities
9. Much of the basic infrastructure at AWE (such as the heating
and electrical systems and a considerable percentage of the office accommodation)
dates back to the 1950s and is increasingly expensive and inefficient
to operate. A great deal of the additional investment will therefore focus
on refurbishment work in this area. In addition, AWE are required to ensure
that we can sustain the Trident warhead in-service throughout its operational
life, and also that the warhead can safely be taken out of service at
the end of its service life. It is possible that during the in-service
life of a warhead, faults can emerge in components as they age. In extremis,
this may require the remanufacture of new replacement components in order
to ensure the safety and performance of the overall warhead. It is therefore
necessary that AWE sustain a basic capability to remanufacture key components
of the Trident warhead. Moreover, when the time comes to withdraw the
Trident stockpile, a range of skills and facilities will be required safely
to disassemble the warheads.
10. An additional focus of the programme at AWE will therefore
be to replace or refurbish some of the basic assembly and disassembly
facilities at Aldermaston and Burghfield. These will include new facilities
for handling high explosives and highly enriched uranium, modernisation
of the assembly/disassembly facilities at Burghfield, and facilities for
non-nuclear components in the warhead.
Investment in Skills
11. The average age of the workforce at AWE has been increasing,
as the generation recruited to meet the initial requirements of the Chevaline
and Trident programmes near the end of their careers. There is therefore
a requirement to recruit new members of staff to ensure that the core
skills within AWE are sustained. Other new staff will be required to assist
the infrastructure sustainment programme and also to operate the new facilities
as they come on stream. We have therefore started a programme of recruitment
and it is planned to increase the current workforce by around 350 staff
per annum until 2007/08, of whom some 70% will be Non-Industrial staff
and 30% Industrial staff.
Summary
12. For as long as the UK remains committed to
retaining a nuclear deterrent, it is essential that we ensure our stockpile
of nuclear weapons remains safe and effective. This programme of additional
investment in skills and infrastructure will ensure that this is achieved,
against the background of the additional demands placed on AWE by the
current and future regulatory regime, the introduction of the moratorium
on underground nuclear tests and the increasing age of the Trident warhead
stockpile, and of the scientists and engineers who support it.
13. This additional investment at AWE is required to sustain
the existing warhead stockpile in-service irrespective of decisions on
any successor warhead. The investment will sustain core skills and facilities
that could also be used in future to develop a successor but no decisions
have yet been made either in principle or practice on this issue.
November 2005
1 O'Nions, Pitman and Marsh, Nature Volume
415 page 853 21 February 2002 Back
2 Supporting Essay 5, Strategic Defence
Review: July 1998 Back
Source: Defence Committee website, http://www.parliament.uk/parliamentary_committees/defence_committee.cfm
Back to the Top of the Page
© 2005 The Acronym Institute.
|