Disarmament Diplomacy
Issue No. 21, December 1997
Implementation of the CWC After the Second Session of the
Conference of States Parties
by Alexander Kelle
Introduction
After entry into force of the Chemical Weapons Convention (CWC)
on 29 April 1997, the First Session of the Conference of States
Parties was held in The Hague in May 1997.(1) The fact that the
Second Session was followed rather closely to the first one - and
not one year after the preceeding one, as it is foreseen in the
Convention - was largely due to the delay of the Russian
Federation's ratification of the CWC. Thus, the date of the Second
Session was chosen to provide an incentive for Russian
ratification, while at the same time it was obvious that one of the
tasks of the Second Session would be the "accomodation" of Russian
interests. One such interest that had been voiced in the past by
Russian officials was their adequate representation in the
structures of the organization set up to implement the CWC, the
OPCW.
A second important task before the Conference was the approval
of the organization's budget for 1998. This task was complicated on
one side by a still lingering debate over the cost of verifying the
destruction of chemical weapons (CW). The other factor which could
be expected to complicate matters was the debate over an adequate
staffing level in the Technical Secretariat (TS). Here, the
interests of the Director General to increase the staffing level
within the TS had to be balanced with some new States Parties'
interest in achieving adequate representation as well as the
interest of the large contributors to the OPCW budget to prevent an
explosion of staff related cost.
The third major task before the Conference was the approval of
draft decisions taken provisionally in the intersessional period.
These decisions were either taken by the Executive Council on a
provisional basis and then transfered to the Conference for
approval, or had been prepared by one of the facilitators,
appointed to conduct informal consultations on several of the
outstanding issues that could not be solved during the First
Session.
The Intersessional Period
The most visible part of the Technical Secretariat's work in
this first intersessional period was the conduct of initial
inspections which took place mostly in CW- and Schedule-1 related
facilites. Only a few Schedule-2 facilities were inspected before
the Second Session of the Conference started on 1 December. The
basis for inspections and visits were the initial declarations
submitted by States Parties. However, until the end of November
only 70 from (then) 102 Member States had submitted such
declarations. What is more, out of the 70 declarations received by
the TS, a considerable number were incomplete. Despite these
deficiencies, some positive surprises were registered in the
declarations submitted. Pursuant to Article IV of the Convention
three States have declared possession of CW (the United States,
India and - most likely - South Korea) (2), which are kept at 26
storage facilities in these three countries. An additional four
States Parties declared CW production facilities pursuant to
Article V of the CWC (the United Kingdom, China, France, Japan).
The number of production facilities that have been declared by the
seven States Parties amounts to 34. Also seven States Parties
declared old and/or abandoned CW (Belgium, China, France, Germany,
Italy, Japan and the United Kingdom).
Notwithstanding the declaration shortcomings, 115 initial
inspections and visits were conducted in 21 Member States; more
than forty inspections took place in the United States alone. Both
the initial inspections in the 34 declared CW production facilites
and the initial inspections of the 26 storage facilities were
completed in the time frames specified in the Convention, i.e.
within 90-120 days for production facilites and 180 days for
storage facilities. However, while initial inspections were
completed within the time-frame specified by the convention, the
same cannot be said for the conclusion of facility agreements.
In addition to initial inspections, continuous monitoring of CW
destruction operations had been established at three US CW
destruction facilities (the Tooele Chemical Agent Disposal
Facility, the Johnston Atoll Chemical Agent Disposal System, and
the Chemical Agent Disposal System at Deseret Army Depot,
Utah).
States Parties are furthermore under the obligation to notify
the TS of any transfer of a Schedule 1 chemical at least 30 days
before the transfer takes place. Until November 20, 62 such
notifications were submitted by either the sending State Party, the
receiving State Party or from both. Only six transfers were
reported by both supplier and recipient, which according to the
wording of the Convention should be the rule. A mere two out of
these six transfers were reported in a timely enough fashion, i.e.
at least thirty days in advance, but even in these cases the amount
of saxitoxin actually shipped was corrected after the transfer had
taken place. Thus, there is still considerable room for improvement
as regards this notification obligation.
In order to bring to life the relevant provisions of the
Convention, i.e. mainly Article XI, the TS has initiated a number
of specific programmes for international cooperation among States
Parties including inter alia programmes related to
facilitating cooperation in the chemical field, facilitation of
bilateral cooperation agreements, a chemical technology transfer
website on the Internet, a database of laboratory equipment being
sought or offered, and a fellowship database and programme for
interns.
The Executive Council (EC) held six sessions during the
intersessional period. During each of the meetings it was presented
with a status report on implementation by the Director General of
the TS. The EC repeatedly urged non-members to sign and/or ratify
the Convention and urged States Parties to submit their
declarations in time and in full. The latter point cannot but cause
some astonishment, since there exists an overlap between EC members
and States Parties who either had not submitted initial
declarations at all or whose declarations are still incomplete. The
US declaration for example did not contain any information on the
country's chemical industry.
In order to allow for the continuous monitoring at CW
destruction facilities, the EC considered and approved five
transitional verification arrangements pertaining to such
facilities in the United States. In addition, the Council approved
two facility agreements for Schedule 1 facilities in Sweden and
Australia respectively. While the approval of these arrangements
falls within the purview of the EC, the final decision on requests
for conversion of CW production facilities for purposes not
prohibited under the Convention rests with the Conference of State
Parties. Consequently, two such requests - one submitted by the
United States, the other by the United Kingdom - were considered by
the EC and then recommended to the Conference for approval.
Other business of the EC included inter alia the
consideration and submission of the Draft OPCW Programme and Budget
for 1998 to the Conference, consultations on the provisional
interim OPCW staff rules as well as the organization's draft
financial rules, discussions on the draft agreement concerning the
relationship between the United Nations and the OPCW, the
consideration of a request for delay in the start of destruction of
a CW production facility, and the manner in which the Convention's
requirements should be implemented as regards the provision of
end-user certificates by States not Party to the Convention prior
to the receipt of Schedule 2 or 3 chemicals from States Parties.
The last three issues could not be solved during the EC meetings
that were held in the intersessional period.
The First Session of the Conference of States Parties
established an Intersessional Procedure for addressing issues that
had remained unresolved during the work of the Preparatory
Commission and the First Session of the Conference. According to
these procedures the Chairman of the Committee of the Whole of the
First Session of the Conference was tasked to designate
facilitators who should address specific unresolved issues.
Although this decision was taken in May it took until mid-September
when the first assignments of facilitators to unresolved issues
took place. In other words, facilitators were left with
approximately ten weeks for consultations in order to solve the
issues on which CWC Member States were unable to agree during four
years of PrepCom work.
Altogether fourteen facilitators were appointed, covering
inter alia issues as wide-ranging as facility agreements for
Schedule 1 and Schedule 2 facilities, types of equipment for
specific types of inspections, issues related to Articles X
(Assistance and Protection Against Chemical Weapons) and XI
(Economic and Technological Development), the terms of reference
for the Scientific Advisory Board, issues related to challenge
inspection, old and abandoned CW, cost of verification in relation
to Articles IV (Chemical Weapons) and V (CW production facilities),
industrial declaration issues, and the conversion of CW production
facilities. Four of the fourteen facilitators were able to produce
compromise proposals, three of which were submitted to the Second
Session of the Conference of States Parties.
The Second Session of the Conference of States
Parties
Eighty-one States Parties, two of which became Member States
during the course of the session (Iran and Russian Federation)
participated in the Second Session of the Conference of States
Parties from 1-5 December in The Hague. In addition, 19 signatory
States, two non-signatories as well as four international
organizations and eight non-governmental organizations attended the
meeting. A number of themes recurred throughout the general debate.
They included the welcoming of recent accessions to the Convention,
the emphasis on the need of all States Parties to comply with their
obligations in time and in full, the concern that still outstanding
issues be resolved as soon as possible to the satisfaction of all
parties concerned, and the urgency of approving a budget for
operations in 1998, including the need to agree on how costs of
verification related to CW facilities are to be reimbursed by the
States Parties concerned, that is States Parties on whose territory
the facilites are located.
Negotiations on the 1998 budget were additionally complicated by
a debate on the appropriate staffing level of the TS and the
requests by some new States Parties who demanded adequate
representation in the staff of the organization. These interests
were confronted by the unwillingness of other States Parties who
shoulder a high percentage of the cost of running the organization
to see the regular OPCW budget increase much above the
provisionally agreed upon level of NLG 122 million for 1998.
Already during past negotiations between the Director General and
the EC the number of requested additional secretariat posts had
roughly been cut by half. The remaining eight general services (GS)
posts, however, were only partially compatible with the interest of
particularly Russia and Iran to be represented in the higher
echelons of the OPCW's structures. A renewed increase in additional
posts was ruled out by members of the Western European and Others
Group (WEOG), who contribute the largest part of the budget.
According to the compromise eventually found in this zero-sum game
the Russian Federation receives one D-1 post (Director for Special
Projects) and Iran - after agreeing to the scale of assessed
contributions for 1998 - got one P-5 post on Emergency Assistance.
As a result, only four of the GS posts requested by the Director
General survived these behind-the-scene deals.
In addition to the debates directly concerned with the
assessable budget for Member States, the debates surrounding the
organization's miscellaneous income, including cost of verification
under Articles IV and V of the Convention will impact on the
regular part of the budget, too. The less States Parties are
willing to live up to their obligation to pay for verification of
their CW stockpiles and production facilities, the more these costs
will have to be covered by all States Parties collectively. The
fact that CW possessor States are on the verge of violating the
"possessor pays" principle enshrined in the Convention does not
prevent both the United States and Russia from attempting to keep
the reimbursable part of verification costs as small as possible.
The bone of contention in this context is the question what exactly
constitutes an inspector's salary. While a compromise solution was
found during the First Session of the Conference of States Parties
in May in the absence of the Russian Federation, the debate was
kept alive during the intersessional period and a proposal
submitted by the facilitator designated to the issue was not able
find the required support. In order to overcome the impasse during
the Second Session of the Conference, an even weaker wording was
negotiated - leaving an ever wider margin for Member States'
interpretations - and debates on the issue will have to continue
within the EC.
Two facilitator's proposals were submitted in addition to the
one on cost of verification: they concerned industry declarations
and issues related to Articles X and XI of the Convention. While
the latter one did not find the approval of the Conference, the
first one did. Accordingly, the term "production" as used in
subparagraph 12 (a) of Article II should be understood to include a
scheduled chemical produced by a biochemical or biologically
mediated reaction. With respect to the declaration of low
concentrations of Schedule 2 and Schedule 3 chemicals contained in
mixtures, States Parties should clearly indicate what concentration
limits were applied for plant site declarations.
The remaining outstanding issues can be subdivided in three
categories: first, issues that were explicitly transfered to the EC
for resolution, for example the reporting of aggregate national
data for Schedule 2 and Schedule 3 chemicals in the context of
industry declarations. Issues whose solution had been overtaken by
events fall in the second category. A case in point is the
negotiation of model facility agreements for Schedule 1 and
Schedule 2 facilities. Two agreements for Schedule 1 facilites have
already been approved by the EC, negotiations on other facilities
are underway. Thus, there is no longer a need for a model
agreement. The third category encompasses all issues that have
again been transferred to intersessional consultations coordinated
by facilitators. Although the new intersessional process to a
considerable degree resembles that of the past, some new provisions
were included to take into account criticism voiced by new States
Parties and provide for a greater regularity in the consultative
meetings and for more transparent procedures giving States Parties
a greater lead-time for preparation. An Iranian proposal to
establish a formal negotiating mechanism with a clear mandate and
time-table according to which issues had to be resolved did not
find the necessary support.
Other business of the Second Session of the Conference included
the election of 20 new members to the EC whose appointments will
take effect in May 1998. In addition, the scale of assessed
contributions was approved, according to which no State Party will
pay more than 25% and 0.01% will constitute the lower floor rate
for calculating the contributions for 1998. After a lengthy debate
the use of two converted CW production facilities for purposes not
prohibited by the Convention was approved by the Conference.
Furthermore, the Terms of Reference for the Scientific Advisory
Board were agreed upon and the Conference provisionally approved
the Operating Procedures of the Confidentiality Commission, subject
to no objection being made by a State Party until 15 January 1998.
The date for the Third Session of the Conference of States Parties
was set for 16 - 20 November 1998.
An Assessment of Progress Made
The triple task of achieving progress in the substantive work of
the organization, reaching agreement on the 1998 budget and
accomodating the late-comers Russia, Iran, and, to a lesser extent,
Pakistan, certainly made this Second Session of the Conference of
States Parties not an easy exercise. These challenges were
aggravated by the fact that the OPCW obviously cannot yet avail
itself of an experienced Technical Secretariat, and that the whole
organization - to some extent - is still in search of itself.
Given the short duration of the Second Session of the Conference
of only one week and taking into account the need to agree on the
1998 budget, much progress in terms of substantive work could not
be expected to occur during the Conference itself. But even if one
takes the compromise solutions proposed and introduced by three of
the facilitators as a yardstick, the result does not look too
promising. Only one of the proposals, the one on industry
declarations, was approved by the Conference. If one looks closer
into the substance of the agreement, one finds one of the issues,
i.e. aggregate national data, referred to the EC, and another one
papered over with a wording providing for an explanation of
national declarations on low concentrations in mixtures. The goal,
however, that had been pursued for years during the preparatory
phase, before entry into force of the Convention, to harmonize
national declarations on low concentrations, obviously was given
up. It may thus happen that the TS gains knowledge of the
concentration limits applied in all national declarations. It
remains to be seen, however, the extent to which declarations will
be comparable.
The accomodation of the interests of new States Parties proved
to be difficult since the demands put forward by these States were
directed either at reducing the costs they have to cover because of
their accession to the Convention, or at achieving a maximum
representation in the organizational structure in terms of post
assignments, or at delaying the implementation of already agreed
upon compromise solutions before their accession, as in the case of
the rules of procedure of the Confidentiality Commission.
Two of the approaches to cut costs, especially for CW possessor
States will very likely be among the most salient issues debated in
The Hague in the foreseeable future: the conversion of CW
production facilities, and the cost of verification as regards the
destruction of CW and CW production facilities. As regards the
conversion of CW production facilites the scrutiny applied during
the Second Session to the US request to use such a converted
facility might be taken as an indicator for debates to come.
Clearly, the preference of China, Pakistan and others is to leave
the conversion of CW production facilities as a remote possibility
in exceptional cases of urgency, while keeping the complete
destruction of such facilities as the norm. The Russian Federation,
in contrast, has explicitly expressed its expectation that future
conversion requests should be handled in a rational, economically
sound way, which would make economic decisions of States Parties -
meaning possessors of CW production facilities - easier.
Similarly, the Russian approach to the reimbursement of costs of
verification of the destruction of CW and CW production facilities
aims at reducing its own share of the burden, regardless of the
provisions of the CWC. While the compromise achieved during the
First Session of the Conference undoubtedly had inspectors'
salaries mentioned as a reimbursable item to be covered by the
inspected State Party, there is considerable concern after the
Second Session of the Conference that the wording agreed to might
allow an interpretation by Russian authorities that salaries of
inspectors do not have to be reimbursed. If this were to happen, it
would amount to nothing less than an amendment of the Convention
through the back door of treaty implementation. Since it is
doubtful that non-CW possessors would allow this to happen, the
issue could well lead to a major crisis over the implementation of
the CWC.
The ad hoc creation of the position of a Director for Special
Projects as well as a Division Head for Emergency Assistance can be
expected to lead to an additional reshuffling of competencies and
support staff in the TS. This undoubtedly will not contribute to
the smooth operation of the Secretariat and might even lead to
requests for additional GS posts, which can in turn be expected to
trigger another lengthy debate on the adequate staffing level of
the TS.
The unequal national implementation of the provisions of the
CWC, if perpetuated, can be expected to either lead to severe
criticisms by those States Parties who fully live up to their
obligations or to an adaptation of their behavior resulting in a
lower stringency with which they implement the provisions of the
Convention. This is especially pertinent in terms of industrial
declarations and, following from that, inspection activities that
industry has to cope with. Being put at a disadvantage as compared
to competitors from other countries will certainly not be tolerated
by industries in States Parties who fully comply with their
obligations under the Convention.
In addition, there is growing evidence that the consistency with
which end user certificates by non States Parties who are
recipients of Schedule-2 and -3 chemicals are requested, varies
greatly. In the case that certificates provided by private
companies and individuals continue to be accepted instead of
governmental end use certificates, the small group of supplying
States who - following to the stipulations of the CWC - insist on
the latter group of certificates can almost certainly be expected
to scale down their requirements, too. By threatening to lower the
overall standard for end use certificates to non States Parties, a
group of CWC Member States is putting at risk a long term security
benefit to be derived from the Convention, i.e. the prevention of
dual use chemicals and equipment finding its way into the CW
program of a proliferant who is not a State Party to the
Convention, for the realization of short term economic benefits.
This is a short-sighted and dangerous approach to implement the
CWC, which has to be prevented by all means available.
Notes and References
1. For an assessment of the First Session see Alexander Kelle:
Setting Up the Organization for the Prohibition of Chemical
Weapons, in Disarmament Diplomacy, Issue No. 15, May 1997,
pp.9-10.
2. See for example The CBW Conventions Bulletin, Issue
No.37, September 1997, pp.8, 24, 33.
Dr. Alexander Kelle is Research Associate at the
Non-Proliferation Project of the Peace Research Institute Frankfurt
(PRIF).
© 1998 The Acronym Institute.
Return to top of page
Return to List of Contents
Return to Acronym Main Page
|